PG Flow Solutions awarded pump supply contract for Aker BP’s Hod project
Published by Nicholas Woodroof,
Editor
Oilfield Technology,
The contract award follows an agreement between a broad political majority in Norway to make temporary changes to the Norwegian petroleum tax system. The Hod development in the Valhall area is Aker BP’s first project to be launched as a direct result of the tax changes.
“It is reassuring to see that operators stay true to their word and initiate projects that were put on hold as a consequence of the extraordinary negative effects caused by the Covid-19 outbreak. New projects allow us, as a supplier, to continuously evolve our offering in order to help make field developments more competitive and to increasingly apply this competence in other industries, such as aquaculture, fisheries and renewables, as we have done over the past decade,” said Steve Paulsen, CEO of PG Flow Solutions.
The planned wellhead platform, to be named 'Hod B', is the second project in the Wellhead Platform Alliance, which was established in 2017 by Aker BP, Kvaerner, ABB and Aker Solutions. The alliance’s first project was the successful Valhall Flank West field development, including its normally unmanned wellhead platform which came on stream in 4Q19.
Under the contract, PG Flow Solutions will deliver miscellaneous pumps to the platform topside, including a pressure equalising pump, freshwater pump, freshwater pressure pump, diesel transfer pump, and one hazardous open drain pump.
PG Flow Solutions has not disclosed the value of the contract, which is subject to government approval of the plan for development and operations (PDO). The company will manage the project out of its facility in Sande, Vestfold, Norway.
The contract is almost identical to the pump system delivery that PG Flow Solutions made to Aker BP and the Wellhead Platform Alliance for the Valhall Flank West wellhead platform in 2018.
“Re-using already proven solutions and development plans reduce costs and risks for both suppliers and the operator. We are therefore very comfortable with the scope of work and delivery schedule indicated for the Hod platform too,” said Mark Tuinman, sales manager – energy, at PG Flow Solutions.
The new Hod platform concept is basically a copy of the Valhall Flank West platform design, with minor changes to functional requirements and some changes resulting from lessons learned from the Valhall Flank West design, commissioning and handover phases.
The Hod field was discovered in 1974; first oil came onstream in 1990 as a tie back to the Valhall Central Complex, producing via a wellhead platform until 2013. The Hod field development project is now working towards a new development of the Hod field, planning to install a new normally unmanned platform that will be tied-back to and remotely controlled from the Valhall Central Complex.
The Hod field is located in Block 2/11 in the southern part of the Norwegian sector of the North Sea, approximately 12 km south of the Valhall Central Complex, 6 km south of the Valhall Flank South platform. The operator is Aker BP AS, holding 90% working interests, with Pandion Energy AS as the sole license partner holding the remaining 10%.
Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/17062020/pg-flow-solutions-awarded-pump-supply-contract-for-aker-bps-hod-project/
You might also like
Halliburton launches Intelli portfolio of wireline conveyed diagnostic well intervention services
Halliburton Company has announced it has introduced the Intelli suite of diagnostic well intervention wireline logging services.