Buru Energy, an oil and gas exploration and production firm, have provided the following weekly update on drilling operations at the Sunbeam 1 well in EP 129 in Western Australia.
Since the last progress report, the well has been drilled ahead in 8.5 inch hole to a measured depth of 1863 ft. The forward operation is to drill ahead to the first casing point planned at approximately 2296 ft and run a cement 7 inch casing.
The Sunbeam 1 well is located in exploration permit EP 129, and completion of the well will satisfy the Year 4 work commitment on that permit. Buru Energy has a 100% equity interest in the well and in EP 129. The well is located some 53 miles south east of Derby and some 11 miles south of the Gibb River Road.
Adapted from press release by Joe Green
Read the article online at: https://www.oilfieldtechnology.com/exploration/29012015/buru-energy-continues-drilling-307/
You might also like
Balmoral Group completes sale of Comtec to Freudenberg Flow Technologies
Following the completion of the deal, Comtec will continue to operate as usual from its existing locations, with no immediate changes to its name, day-to-day activity, customer contracts, delivery schedules, staffing levels or points of contact.