West Erregulla JV secures drilling rig
Published by Nicholas Woodroof,
Editor
Oilfield Technology,
West Erregulla 3 is due to spud during 3Q20 with mobilisation to commence after civil works are complete for the drill pad construction.
West Erregulla 4 will follow shortly after, with the timing dependent on the regulatory approvals process. West Erregulla 5 planning is also underway, with a decision by the JV due no later than 30 November 2020 to make this well a firm commitment. Strike has procured a contingent drilling slot on the Ensign 970, an ADR-1500 model rig, for this activity.