Aibel awarded multiple FEED contracts by Equinor

Published by , Editor
Oilfield Technology,


Equinor has signed several FEED contracts with Aibel worth around NOK5 billion, including options.

Aibel has been awarded a contract for FEED for the unmanned processing platform at the Krafla field. The award is a continuation of the pre-FEED contract they were awarded in 2020. The study will form the basis for tying an unmanned platform to the Aker BP-operated platform on the NOA field. The study is valued at just above NOK180 million.

The Krafla field development will be one of the biggest development projects on the NCS in the planned realisation period. The development will represent a major part of the NCS investment level and help maintain the activity level in the industry.

In June 2020, the licensees in Krafla, NOA, and Fulla agreed on a coordinated development of the fields, of which Equinor is operator of Krafla in the north and Aker BP is operator of NOA Fulla in the south.

The planned development concept involves an unmanned production platform (UPP) to which subsea installations on Askja, Krafla, and Sentral will be tied in. Operations will be run from Equinor’s operations centre at Sandsli in Bergen, representing a new and important technology development providing a more cost-effective field development solution compared to conventional platform concepts.

The power demand of Krafla and NOA Fulla will be met by power from shore through a submarine power cable from Samnanger in Vestland county.

Plans call for an investment decision to be made at the end of 2022. Given an investment decision, the supplier selection for the implementation contract will also be made in 2022.

Aibel has also been awarded a FEED study, including an option for an extended FEED study and the actual implementation of topside modifications for tying the Asterix discovery to the Aasta Hansteen platform.

The total value of the FEED study is calculated to be just above NOK75 million. The implementation option is calculated to exceed NOK1 billion, including for example a 430-t module to be assembled in the North Sea Hall at Aibel’s yard in Haugesund.

Located in 1350 m of water in the Norwegian Sea, Asterix is a subsea development taking place around 80 km west of the Aasta Hansteen platform. The project will help extend the life of the Aasta Hansteen field, which will drop below plateau production in 2026 when Asterix is to be phased in.

Plans call for the gas to be processed and then transported to the market via the Polarled pipeline to the terminal at Nyhamna. The chosen concept includes for example a subsea template with three gas producers and a pipeline of 80 km.

An investment decision is scheduled for the autumn of 2022.

The Gina Krog licence partners have decided to invest in a new oil export solution on the Gina Krog field. A new 23-km pipeline between Gina Krog and Sleipner A (SLA) will replace the existing Rangfrid floating storage and offloading vessel (FSO) in 2024. Aibel has been awarded an implementation contract for modifications on Gina Krog and Sleipner A for tying the platforms together by the new pipeline.

Valued at close to NOK500 million, this contract is expected to employ around 70 people during the next three years. This is the fourth contract awarded to Aibel for modifications in the Sleipner area, where Equinor is cooperating with Aibel in a portfolio organisation.

Removal of the current vessel solution will reduce CO2 emissions from the field by around 18 000 tpy. The new pipeline will strongly reduce annual operating costs from the field while helping extend field production.

On behalf of the operator Gassco and the Gassled partnership, Equinor has awarded Aibel a FEED contract for electrification of turbines and pressure boilers at the Kårstø processing plant.

The contract was awarded on 12 October however it was officially signed on 23 November. The value is estimated at NOK130 million for the FEED study, which will form the basis for a cost evaluation before a final investment decision is to be made at the end of 2022.

An implementation option has also been awarded at a preliminary estimated value of more than NOK3 billion. The study is expected to employ around 85 people on average, and up to 600 during the implementation phase.

The Kårstø electrification project aims to reduce CO2 emissions by close to 500 000 tpy.


Read the latest issue of Oilfield Technology in full for free: Issue 3 2021

Oilfield Technology’s third issue of 2021 starts with a report from Wood Mackenzie focusing on the upstream industry’s fortunes in Asia-Pacific. The rest of the issue is dedicated to features covering offshore engineering, coiled tubing, frac technology, completion technologies, water management, well placement and much more.

Exclusive contributions come from Wild Well Control, Cudd Pressure Control, TMK, NOV, Archer, Tendeka, TETRA Technologies and more.

Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/24112021/aibel-awarded-multiple-feed-contracts-by-equinor/

You might also like

 
 

Embed article link: (copy the HTML code below):