Woodside: SNE Field Development–Phase 1 commences FEED activities
Published by Aimee Knight,
Editorial Assistant
Oilfield Technology,
The FEED work involves undertaking activities required to finalise the costs and technical definition for the proposed development to enable a final investment decision, targeted for mid-2019.
Woodside CEO Peter Coleman said the decision to commence FEED activities was a significant step towards the development of Senegal’s first oil project.
“We plan to progress the SNE development towards the earliest possible commercialisation of the discovered resources. Completing FEED activities will be a key enabler of a final investment decision.
“We are also excited to be moving forward on the SNE development as it is a key pillar of Horizon Two of our growth strategy.
“As part of FEED activities, the RSSD joint venture will continue working with the Government of Senegal, local communities and our contractors to realise the potential opportunities and benefits from this nationally significant development,” he said.
Commencing FEED activities follows approval by the Senegalese Minister of Petroleum and Energies of Woodside assuming the role of operator, and the RSSD joint venture’s submission of the SNE Field Development and Exploitation Plan to the Government of Senegal.
The SNE development concept is a stand-alone floating production storage and offloading vessel (FPSO) facility with supporting subsea infrastructure. It will be designed to allow subsequent SNE development phases, including options for gas export to shore and for future subsea tiebacks from other reservoirs and fields.
Phase 1 of the development will target an estimated 230 million bbl of oil resources (P50 gross) from the lower, less complex reservoirs and an initial phase in the upper reservoirs. The FPSO is expected to have a capacity of around 100 000 bbl/d, with first oil production targeted in 2022. In parallel to the commencement of FEED activities, the RSSD joint venture continues to progress project financing and the Environmental and Social Impact Assessment.
Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/17122018/woodside-sne-field-development-phase-1-commences-feed-activities/
You might also like
Wood signs a trio of global engineering and project delivery agreements with bp
John Wood Group PLC has signed three major agreements with bp to provide engineering and project delivery services for their capital projects worldwide.