Valhall QP topside removed

Published by , Editor
Oilfield Technology,


Aker BP has announced that the original accommodation platform at Valhall (QP) in the southern part of the North Sea was safely removed by the giant vessel Pioneering Spirit last week. This was the first of the original structures at Valhall to be removed as part of the modernisation of the Valhall field centre.

Executed in the morning of Friday 14 June, the single-lift operation took 2 hours to complete from positioning Pioneering Spirit around the 3800 t platform to the moment of the lift. The actual 'fast lift' of the topsides took 9 seconds. The 109 t bridge connecting the QP topsides to the neighbouring drilling platform was removed using one of the vessel’s cranes on Tuesday 11 June.

"Together with Allseas and the team at Pioneering Spirit, we have successfully concluded two years of engineering, planning and pre-lift preparations. The safe and efficient removal of the QP platform is an important milestone for Valhall and for Aker BP", said Per Mikal Hauge, Vice President Valhall asset.

Removal of the QP topsides is the first job for Pioneering Spirit under the frame agreement which Allseas signed with Aker BP in 2017 to provide transport, installation and removal services for the Valhall field. The QP topside will be transported to and disposed at the Kvaerner disposal yard at Stord.

The Valhall field was discovered in 1975 and put into production in 1982 with three installations; a process / production platform, a drilling platform and an accommodation platform (QP). More recently a wellhead platform (WP) and Injection platform (IP) was installed. Lastly, production from the new process / accommodation platform (PH) started in January 2013.

The QP topsides is the first of the three original structures to be removed from the field centre. The remaining platforms at the field centre – IP, WP and PH – and the Flank platforms will produce for many, many years to come.

Valhall and Hod have passed 1 billion boe (oil, gas and NGL) produced.

Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/17062019/valhall-qp-topside-removed/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Offshore news North Sea oil news Oil rig news Upstream project news