Skip to main content

Trelleborg: Ensuring precision floatover mating

Published by , Digital Assistant Editor
Oilfield Technology,


As the oil and gas industry is forced to work harder to extract oil from around the globe, reliance on reserves in remote offshore locations is increasing. As a result, there’s been a resurgence in floatover installation practices and it’s becoming the technique of choice to install topsides into place, versus using heavy lift cranes. Its impact in terms of overcoming logistical challenges in the case of complex and costly platform manoeuvres is revolutionising engineering at sea.

JP Chia, Engineering Manager at Trelleborg’s engineered products operation considers the factors affecting operators and looks at how use of floatover technology can help reduce costs and eliminate downtime.

Operators are demanding bigger and heavier platforms to increase the effectiveness of their exploration and production. Currently, one in six topside units weighs more than 12 000 t, with the world’s heaviest weighing an enormous 47 830 t. This means that floatover installations are growing in numbers, as it becomes the most efficient and effective way to install the increasing size of the platform.

Indeed floatover installation techniques are being favoured over the traditional crane method, not least because they can handle over three times the weight, but also because the cost of crane time can run into several hundred thousand dollars per day; a cost that is immediately eliminated with a floatover. Further, only one transportation vessel is needed for installation and nearly all of the work to construct the topside can be completed in the fabrication yard, resulting in lower labour costs.

Taking all of these factors into account, according to a research paper by marine contractor Dockwise Ltd, use of floatover installations between 2014 and 2018 is predicted to grow by 38% so that an estimated 52% of all installations will be conducted in this manner.

Margin of error

Expert management and execution of a floatover installation is crucial to ensure that both the topside and the jacket legs are safely and securely fitted together. This brings some complexities with it, and failure to get this right the first time, every time, means there are implications for the safety, timeline and cost of the job and the personnel involved.

Critical to this is the mating hardware used to connect the jacket with the topside. Leg mating units (LMUs) are in operation for a short duration, but if the product fails in this small window, huge damage can be caused and long delays may result. Consisting of steel structures incorporating engineered elastomeric pads, LMUs make the transition possible by dampening the forces created, as the topside’s load is transferred to the jacket structure.

The elastomeric pads are designed to take up the static and dynamic forces of the topside structure, as well as the horizontal forces due to open sea motions during the floatover mating operation. The vertical elastomer pads are normally complemented with horizontal elastomeric pads to cater for this movement.

Using data provided by an offshore consultant on the expected loads and movements, the elastomeric pads must be carefully engineered and calculated with non-linear finite element analysis (FEA), to achieve the expected spring stiffness for this crucial task. Similarly, the correct formula of rubber must be used to cater?to the loads placed on it. Polymer is very complex and unpredictable and only a supplier with specific knowledge and understanding of polymer behaviours can supply the most suitable solution for the job. This attention to detail is vital, especially in a market where there is very little margin for error.

Likewise, rubber deck support units (DSU’s) are also important components for safe floatover operations. The topside is loaded onto the transportation vessel with a deck support frame and the DSUs are then placed between them to absorb the weight of the topsides. This enables the LMUs and DSUs to work together in sync during the mating process. When the transport barge reaches the installation site and manoeuvres between the jacket legs and starts to ballast, decompression occurs on the DSUs and vertical compression on the LMUs.

Finally, rubber fender systems are commonly used to absorb the impact of the heavy vessel and the jacket legs as it moves in the tidal swell during the mating operation. Some sway and surge fenders can contribute to the failure of a floatover process if not designed properly, by not sufficiently protecting the platform jacket to which the topside is mated. If the jacket legs are compromised, long and costly delays can be caused to a project as was witnessed in the South China Sea.

Case study: Soaking up kinetic energy in the South China Sea

Trelleborg’s engineered products operation fast-tracked the manufacture, testing and delivery of its floatover mating technology for a major oilfield project in the South China Sea, in just four months. The project previously experienced an unsuccessful floatover operation in August 2013, causing structural damage to the barge and the jacket. As such, an overhaul of the floatover system was required and Trelleborg was contracted to provide its customised solutions to the project as quickly as possible. This allowed the stalled project to quickly and safely commence installation, ending an eleven-month delay and an escalation of costs.

Contracted by Ashburn Offshore Oil & Gas Equipment & Engineering Company Ltd., Trelleborg designed, fabricated and delivered eight LMUs – four inner legs and four outer legs – and floatover fenders. With the topside weighing 12,500 tonnes, each LMU was designed with a load capacity of 1,800 tonnes.

The project suffered setbacks during its initial installation attempt and it was at this point that Trelleborg was contracted to supply its floatover technology. It also supplied customised sway and surge fenders to absorb any kinetic forces the floatover barge would exert on the jacket. This ensured that the floatover process, especially when installing the topside onto the jacket, was completely safe for both the topside and jacket structures. In conjunction with its fenders, the high performance LMUs were easily able to support the weight of the topside and maintain stability during installation, even in high sea swell conditions.

There was a lot of pressure to get the project right in light of previous events and the project required fast, quality solutions that would perform perfectly. The Trelleborg solution guaranteed reliability and provided a rapid method to get the platform online as fast as possible given previous delays.

Trelleborg managed to decrease its throughput time from manufacture to delivery when the urgency of the project was realised to ensure a concise and fast turnaround. Extra shifts and staff were assigned to ensure the contractor’s needs were met. Trelleborg manufactured, tested and delivered the solutions in just four months, making the project’s second floatover process a success.

Bian Shaoping, Manager of the Market Structure Department at Ashburn, commented: “We’ve received excellent feedback about Trelleborg’s products following the successful installation, due to its reliability, safety and ability to provide peace of mind.”

Finding the right solution

It’s clear from real life examples that finding the right partner with the right capabilities is crucial to success, and that failure to do so can quite literally lead to the collapse or stalling of a project. Failure costs time and money, and in some cases delays oil exploration for extended periods of time.

It’s not just a case of finding a partner with the right capabilities – crucial to success is how early a partner with the expertise to deliver to a brief is involved. In addition, rather than saving on the cost of the components involved, it’s even more valuable to work with suppliers that have a strong track record and proof of capability. If the manufacturer is not engaged at the front-end engineering design (FEED) stage, project decisions can be made that could negatively impact the overall design and performance of the platform.

In the case of floatover installations, the rubber components; LMUs, DSUs and sway and surge fenders must have a high performance specification. A supplier with in-house rubber compound technology can produce the very best solution, on a project-by-project basis. Each solution should be purpose engineered to meet the project requirements and to eliminate the chance of failure and costly delay. Solutions must be right first time, every time. Calculations and analyses need to be conducted so that components are in-line with the size of the topside and its increasing weight accordingly.

Testing is also imperative as weather and sea conditions are affected by locations, impacting on vessels in numerous ways. It’s important to choose a supplier with the ability to perform full-size LMU compression testing, to maximum design-factored load capacity and to test all LMU elastomeric pads to verify their behaviour prior to installation.

As platforms continue to get bigger and heavier, the time, cost and logistical challenges surrounding them means the engineering expertise behind their deployment is in much greater demand. That extends to the rubber components that have the ability to make or break a floatover installation. Working with a global supplier with the right solutions, expertise and control over end-to-end processes means that operators can rest assured they can keep up with floatover practices against the backdrop of the challenges they increasingly face.

Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/13012017/trelleborg-ensuring-precision-floatover-mating/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Upstream news Oil & gas news