ExxonMobil to proceed with Liza Phase 2 development offshore Guyana

Published by , Editorial Assistant
Oilfield Technology,


ExxonMobil has said that it has funded the Liza Phase 2 development offshore Guyana after it received government and regulatory approvals. Liza Phase 2 will produce up to 220 000 bpd and further capitalise on the development potential of the Stabroek Block, where ExxonMobil estimates producing more than 750 000 bpd by 2025.

A total of six drill centres are planned as well as approximately 30 wells, includ-ing 15 production, nine water injection and six gas injection wells. Phase 2 startup is expected in mid-2022 and will develop approximately 600 million bbl. Liza Phase 2 is expected to cost US$6 billion, including a lease capitalisation cost of approximately US$1.6 billion, for the Liza Unity floating production, storage and offloading (FPSO) vessel.

“With the government of Guyana and our partners, ExxonMobil is bringing upstream capabilities to build upon Phase 1 and further develop the shared value of Guyana’s resources,” said Liam Mallon, president of ExxonMobil Upstream Oil & Gas Company. “We are actively pursuing significant development potential from numerous discoveries in the Stabroek Block.”

Liza Phase 1 remains on track to achieve first oil by the first quarter of 2020. It will produce up to 120 000 bpd at peak rates utilising the Liza Destiny FPSO, which is expected to arrive offshore Guyana in the third quarter of 2019.

Pending government and regulatory approvals, a final investment decision is expected later this year for a third phase of development, Payara, which is expected to produce between 180 000 and 220 000 bpd with startup as early as 2023. ExxonMobil is evaluating additional development potential in other areas of the Stabroek Block, including at the Turbot area and Hammerhead.

By the end of 2019 ExxonMobil will have four drill ships operating offshore Guyana. Following well completion activities at the recently announced Yellowtail discovery, the Noble Tom Madden will move to the Hammerhead-2 well. The Stena Carron is completing a well test at the Longtail-1 discovery, and will then move to the Hammerhead-3 well.

Later in 2019, the Stena Carron will drill a second well at the Ranger discovery. The Noble Bob Douglas drillship is completing development drilling operations for Liza Phase 1. ExxonMobil will add another exploration drillship, the Noble Don Taylor, in the fourth quarter of 2019.

As the projects proceed, the partners’ investment in the Guyanese economy continues to increase. The number of Guyanese nationals supporting project activities more than doubled in 2018 to more than 1000. ExxonMobil and its co-venturers spent nearly US$60 million with more than 500 Guyanese vendors in 2018. More than 1500 Guyanese companies are registered with the Centre for Local Business Development, which was founded by ExxonMobil and its co-venturers in 2017 with the mission of supporting local businesses to become globally competitive.

Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/07052019/exxonmobil-to-proceed-with-liza-phase-2-development-offshore-guyana/