LUKOIL commissioned first production well at the phase 2 of Filanovsky field

Published by , Deputy Editor
Oilfield Technology,


LUKOIL has completed the construction and commissioning of the first well at the Phase 2 of Vladimir Filanovsky field in the Caspian Sea.

This is a production single bore horizontal well with the measured depth of 3.5 km. The horizontal section of the well is 1.2 km. The initial well flow reached 2.4 thousand t of oil/d. As a result, the daily oil production at the field increased to 16.8 thousand t. 

As of 31 January, the company started to drill an injection well. Further execution of the drilling program at the Phase 2 of the field's development will allow to stabilise production at the designed plateau of 6 million t on an annualised basis.

Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/02022018/lukoil-commissioned-first-production-well-at-the-phase-2-of-filanovsky-field/

You might also like

Shell invests in Nigeria offshore gas development

Shell Nigeria Exploration and Production Co. Ltd (SNEPCo), a subsidiary of Shell plc, together with Sunlink Energies and Resources Ltd, have taken a final investment decision (FID) on the HI gas project offshore Nigeria.

 
 

Embed article link: (copy the HTML code below):