Statoil makes final investment decision on Shah Deniz Stage 2

Published by , Editor
Oilfield Technology,


The BP-operated Shah Deniz consortium has announced the final investment decision for the Stage 2 development of the Shah Deniz gas field, in the Caspian Sea, offshore Azerbaijan. This decision triggers plans to expand the South Caucasus Pipeline (SCPX) through Azerbaijan and Georgia, to construct the Trans Anatolian Gas Pipeline (TANAP) across Turkey and to construct the Trans Adriatic Pipeline (TAP) across Greece, Albania and into Italy. Together these projects will create a new Southern Gas Corridor to Europe. The total cost of the Shah Deniz Stage 2 and SCP Expansion projects will be around US$ 28 billion.

"The Shah Deniz Stage 2 project is a significant project which will make Azerbaijan's large gas resources available for the European market, it brings benefits for customers and creates value for the partners", says Helge Lund, president and CEO of Statoil.

Statoil has today also signed an agreement to divest a 10% share of its 25.5% holdings in the Shah Deniz and the South Caucasus Pipeline. The buyers are SOCAR (6.7%) and BP (3.3%). Statoil will as part of this transaction receive a total cash consideration of USD 1.45 billion. Effective date of the transaction is 1.1.2014.

"The divestment corresponds with our strategy of portfolio optimisation based on rigid prioritisation of future investment, and capturing value created from a significant gas position", Lund continues.

Statoil will not participate as an investor in TANAP.

"We have considered our potential positions throughout the project's value chain, balancing economics and risks to identify the optimal participation," says Lund.

Statoil holds a 20% share in TAP AG, the owner of Trans Adriatic Pipeline (TAP), who develops the pipeline for transport of gas from Turkey to Southern Europe.

The current Statoil equity production (gas and condensate) from Shah Deniz as per third quarter 2013 is 56 000 boepd.

The Shah Deniz stage 2 project includes offshore drilling and completion of 26 subsea wells and construction of two bridge-linked platforms. Onshore there will be new processing and compression facilities at Sangachal.  16 billion cubic m a year (bcma) of gas produced from the Shah Deniz stage 2 project will be carried some 3500 km to provide energy for millions of consumers in Georgia, Turkey, Greece, Bulgaria and Italy. First gas is targeted for late 2018, with sales to Georgia and Turkey. First deliveries to Europe will follow approximately a year later.

Statoil entered Azerbaijan in 1992 and is a partner with an 8.56% share in the oil producing Azeri-Chiraq-Guneshli (ACG) field, the Shah Deniz gas field with a 15.5% share, and the corresponding pipelines Baku-Tbilisi-Ceyhan (BTC) and South Caucasus Pipeline (SCP).

Adapted from a press release by David Bizley

Read the article online at: https://www.oilfieldtechnology.com/exploration/17122013/statoil_makes_final_investment_decision_on_shah_deniz_stage_2/