Comet Ridge provide update on Albany 1 drilling operations

Published by
Oilfield Technology,


  • Well currently at 1336 m and drilling ahead in 8 1/2 in. hole.
  • Total depth prognosed to be approximately 2775 m.

Comet Ridge Limited has provided an update on the ongoing drilling operations at the Albany 1 well in the north eastern Galilee Basin. At 0600 hrs this morning, the rig was drilling ahead at 1336 m in the 8 1/2 in. intermediate hole section, part-way through the Jochmus Formation.

Since the last drilling update, at 0600 hrs on Monday 21 May 2018, drilling operations have seen:

  • Continued drilling of 12 1/4 in. hole from 711 m to surface casing point at 747 m.
  • Running and cementing of 9 5/8 in. surface casing.
  • Installation and testing of wellhead components and well control equipment at surface.
  • Drilling ahead in 8 1/2 in. hole from the surface casing point to the current depth of 1336 m.

The total depth (TD) of the well is prognosed to be approximately 2775 m. Figure 1 below details the position of the Albany 1 well in the Galilee Basin and also the position of the well on the structure (inset).

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/29052018/comet-ridge-provide-update-on-albany-1-drilling-operations/

You might also like

bp to sell interest in bp-Husky Toledo Refinery to Cenovus

Cenovus will pay US$300 million for bp’s stake in the refinery, plus the value of inventory, and take over operations when the transaction closes, which is expected to occur later in 2022. bp and Cenovus will also enter into a multi-year product supply agreement.

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Upstream news Upstream drilling news Oil & gas news