Oseberg Vestflanken 2 leaves HFG

Published by , Digital Assistant Editor
Oilfield Technology,


The topside for the Oseberg Vestflanken 2 Unmanned Wellhead Platform recently sailed out from Heerema Zwijndrecht. The jacket followed on 26 June.

In 2016, Statoil awarded Heerema the contract for the Engineering, Procurement & Construction as well as the transport and installation of the platform. HFG carried out the engineering, based on a lean and innovative concept, which was developed by HFG Engineering and Statoil in close cooperation. Fabrication started in June 2016. At the Zwijndrecht yard, HFG constructed within a year the 900 t topside with a length of 25 m, a width of 23 m and a height of 20 m and a 4400 t jacket with a height of 138 m and a foot print of 36 x 36 m. Heerema Marine Contractors (HMC) executes the transportation to the offshore location and will also perform the installation with HMC’s SSCV Hermod in the Oseberg area in the Norwegian part of the North Sea, about 130 km north-west of Bergen.

“We are proud of what we have accomplished for Statoil,” commented Koos-Jan van Brouwershaven, CEO of HFG. “Our design of an unmanned wellhead platform with no facilities, helicopter deck or lifeboats represents a new solution with great possibilities. It meets the challenges of lower investment costs and higher efficiency requirements. The success of this project is due to the excellent cooperation with the client and the combined strength of HFG and HMC from engineering up to and including the installation. Together with Statoil, we come to the best result in all aspects by joining forces.”

The final destination of the Oseberg Vestflanken 2 Unmanned Wellhead Platform is the Norwegian part of the North Sea, approximately 8 km northwest of the Oseberg Field Centre.

It is the first of three planned phases for developing the remaining reserves in the Oseberg area. The Oseberg Vestflanken Development consists of an unmanned wellhead platform with 10 well slots.

Two existing subsea wells will also be reused. The well stream will be routed to the Oseberg Field Centre via a new pipeline, and the wells will be remote-controlled from the Field Centre. The field development will provide 110 million boe. Production start is scheduled for 2Q18.

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/26062017/oseberg-vestflanken-2-leaves-hfg/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Upstream news Oil & gas news