ExxonMobil starts oil production at Erha North Phase 2 project

Oilfield Technology,



Exxon Mobil Corporation has announced that its subsidiary, Esso Exploration and Production Nigeria Limited, has started oil production ahead of schedule at the Erha North Phase 2 project offshore Nigeria.

The Erha North Phase 2 project is a deepwater subsea development located 60 miles offshore Nigeria in 3300 ft of water and four miles north of the Erha field, which has been producing since 2006. The Erha North Phase 2 project includes seven wells from three drill centres tied back to the existing Erha North floating production, storage and offloading vessel, reducing additional infrastructure requirements.

The project is estimated to develop an additional 165 million bbls from the currently producing Erha North field. Peak production from the expansion is currently estimated at 65 000 bpd and will increase total Erha North field production to approximately 90 000 bpd.

“Executing successful projects such as Erha North Phase 2 ahead of schedule and under budget results from ExxonMobil’s disciplined project management approach and expertise,” said Neil W. Duffin, president of ExxonMobil Development Company. “We are able to create additional shareholder value by optimising existing infrastructure, which reduces capital spending requirements and improves capital efficiency.”

Duffin said the ahead-of-schedule startup was supported by strong performance from Nigerian contractors, which accounted for more than US$2 billion of project investment for goods and services, including subsea equipment, facilities and offshore installation.

“These contracts are bringing direct and indirect benefits to the Nigerian economy through project spending and employment, consistent with project objectives,” Duffin said.

ExxonMobil expects to increase its global production volumes this year by 2 percent to 4.1 million boe/d, driven by 7% liquids growth. The volume increase is supported by the ramp up of projects completed in 2014 and the expected startup of major developments in 2015.

The Erha North field was discovered in 2004 and initial production commenced in 2006. Operator Esso Exploration and Production Nigeria Limited holds a 56.25% interest in Erha North Phase 2, while Shell Nigeria Exploration and Production Company holds the remaining 43.75% share.

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/16092015/exxonmobil-starts-oil-production-at-erha-north-phase-2-project/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Oil & gas news