Prospera has completed the drilling of four horizontal wells of the ten well multi-pad infill drill programme. These wells encountered structure and pay as expected with excellent oil show throughout the pay. The drilling technique tweaked from the pilot wells were executed efficiently and ahead of schedule. Lasso Drilling Corporation achieved effective synergy with Prospera to attain efficiency. These drilled horizontals are being completed and tied-in to existing infrastructure. Turnaround time to bring the production online is approximately two to three weeks; two horizontal wells are already completed. The production will be brought on gently initially to optimise recovery due to the heavier fluid properties. The full deliverability can be attained, approximately, over a three-month period. The next set of four horizontals are to commence within one week, barring any weather-related delays.

This multi-pad infill drill programme stems from a comprehensive geological, seismic, and reservoir management delineation. The infill programme is designed to optimise recovery with optimum wells in a cost-effective manner, while also aligning with planned enhanced and improved recovery techniques. As previously announced, this ten well programme can approximately add an additional 750 bpd at a low decline to Prospera’s current 900+ boe/d. This infill development is intended to accelerate production and recovery to capture the significant remaining heavy oil reserves (400 million bbls).

The medium-light oil spud will follow the heavy oil horizontal well transformation from vertical wells in the latter part of this month. These slanted drills are awaiting the preparation of the new leases, surface facilities, and connecting pipelines. The medium-light oil development entails six to eight directional wells that can add an additional 600 bpd (gross) at 50%, diversifying Prospera’s product mix and improving margin.

Overall, this Phase 2 development plan will allow Prospera Energy to become a low-cost producer with a significant increase in production. Prospera’s primary focus subsequent to increased production and corresponding revenue is to address all legacy arrears (especially, land owners and local community vendors), stay current with payables, and maintain services with comparable terms. Meanwhile, PEI will continue to execute its liability management plan to reduce the asset reduction obligations.

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/12092023/prospera-energy-inc-announces-horizontal-infill-drilling-programme-update/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Upstream drilling news Oil & gas news