Total, operator of Block 17 in Angola, together with the Angolan National Oil, Gas and Biofuels Agency, has announced the start of production from the Zinia Phase 2 short-cycle project, connected to existing Pazflor’s FPSO.

The project includes the drilling of nine wells and is expected to reach a production of 40 000 bpd by mid-2022.

Located in water depths from 600 to 1200 m and about 150 km from the Angolan coast, Zinia Phase 2 resources are estimated at 65 million barrels of oil.

The development of this project was carried out according to schedule and for a CAPEX more than 10% below budget, representing a saving of US$150 million. It involved more than 3 million manhours of work, of which 2 million were performed in Angola, without any incident.

“The successful start-up of this project, despite the challenges that have arisen as a result of the pandemic, demonstrates Total’s commitment to ensure a sustainable output on Block 17, for which the production license was recently extended until 2045. Zinia Phase 2 project reflects the quality of short cycle projects in Angola with high return on investment”, said Nicolas Terraz, President Africa, Exploration and Production at Total.

Paulino Jerónimo, CEO of the National Oil, Gas and Biofuels Agency, commented as follows, “Zinia Phase 2 is a key project for Angola that comes at the right time to sustain the production of the country. We welcome our collaboration with Total in Angola, that keeps investing with its partners in the development of the country oil resources”.

Block 17 is operated by Total with a 38% stake, alongside with Equinor (22.16%), ExxonMobil (19%), BP Exploration Angola Ltd (15.84%) and Sonangol P&P (5%). The contractor group operates four FPSOs in the main production areas of the block, namely Girassol, Dalia, Pazflor and CLOV.


Read the latest issue of Oilfield Technology in full for free: Issue 1 2021

Oilfield Technology’s first issue of 2021 begins with a look at US tight oil’s prospects this year. The issue then moves on to cover completions technology, production forecasting, electric fracturing, sand recovery and more.

Exclusive contributions come from Rystad Energy, Archer, Weatherford, Halliburton, CGG, NOV, TETRA Technologies, Clariant and more.

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/06052021/production-begins-at-zinia-phase-2-project-offshore-angola/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Upstream news Offshore news Upstream project news Oil & gas news