Eni has announced that Zohr 5x, the fifth well on Zohr structure has been successfully drilled to the final TD of 14 271 ft (4350 m). The Zohr 5x well is located in 1538 m of water depth and 12 Km south west from the discovery well Zohr 1x.

The well proved the presence of a carbonatic reservoir and gas accumulation also in the South-Western part of the Zohr mega-structure encountering about 590 ft (180 m) of continuous hydrocarbon column in the carbonate sequence with excellent reservoir characteristics. The results are confirming the potential of the Zohr Field at 30 Tcf OGIP.

The well was also successfully tested opening 90 m of reservoir section to production. The data collected during the test confirmed the great deliverability of the Zohr reservoir, in line with the Zohr 2 well test, producing more than 50 million ft3 limited only by the constraints of the drilling ship production facilities.

In the production configuration, the well is estimated to deliver up to 250 million ft3 per day.

The drilling campaign on Zohr will continue in 2016 with the drilling of the sixth well that will ensure the accelerated start up production rate of 1 billion ft3 per day. The steady progress of the project execution is confirming the schedule expected to reach the first gas by the end of 2017.

Eni, through its subsidiary IEOC Production B.V., holds a 100% stake in the Shorouk Block. Petrobel is operating the activities on behalf of the Petroshorouk company, an equal joint venture between IEOC and the state company Egyptian Natural Gas Holding Company (EGAS).

Eni has been present in Egypt since 1954 where it operates through IEOC Production BV. The equity production in the country was in 2015 about 200 000 boe/d.

For more information, please visit://https://www.eni.com


Adapted from a press release by Louise Mulhall

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/05092016/eni-successfully-drilled-and-tested-zohr-5x/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Oil & gas news