OKEA expects delays in first oil from Yme field
                            
                                
                                
                                        
                                            
                                        
                                
                                    
                                        Published by Nicholas Woodroof,
                                        Editor
                                        
                                    
                                Oilfield Technology,
                                
                            
                        
The Gjøa field (12% WI) is exempted from the production limitations.
In order to re-optimise the operation and production at Draugen, bi-annual maintenance shutdown has been moved from September to late June. On this basis, OKEA maintains the production guidance for 2020 of 14 000 – 15 000 boe/d on average for the year. The revised shutdown schedule results in a postponement of an OKEA lifting which was previously planned for June to August which, due to revenue from sale of petroleum products being recognised in the financial statements at lifting, will increase the risk of a breach in bond covenants for 2Q20.
Implementation of Covid-19 related infection control measures and travel restrictions has resulted in significantly lower availability of personnel at the Aker Solutions yard in Egersund, Norway, where the Maersk Inspirer rig for the Yme project (15% WI) is undergoing an upgrade. Consent for using the rig on the Yme field was given by the Petroleum Safety Authority on 18 May. In case of prolonged restrictions, in addition to the inherent schedule risk of all large modification projects, OKEA expects first oil for Yme to be delayed to the first half of 2021.
Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/29052020/okea-expects-delays-in-first-oil-from-yme-field/
You might also like
Eni and PETRONAS sign investment agreement to establish new JV Satellite Co. in Indonesia and Malaysia
The agreement follows the Framework Agreement signed by the two companies on 17th June 2025 and establishes a new entity that will manage 19 assets: 14 in Indonesia and five in Malaysia - representing significant enterprise value.