Production disrupted at Merakes gas field
Published by Nicholas Woodroof,
Editor
Oilfield Technology,
The disruption, caused by a sand blockage, had been going on since earlier this month and the facility is set to reopen in a day or two, said Julius Wirato, the deputy head of operations at the state's regulator SKK Migas.
"There's a subsurface issue with one of the wells in Merakes, we are working to fix it," Wirato told Reuters.
Wirato said 50% of production would be recovered soon, hopefully in the next few days.
"But for 100% recovery... will take quite some time, around six months," he added.
Indonesia's gas distribution is already compromised due to a separate disruption in Natuna that happened in July, impacting gas supplies and electricity prices in neighbouring Singapore.
The Merakes project, operated by Italy's Eni, had only started gas production in April and guaranteed a production capacity of 450 million ft3/d.
Eni did not immediately respond to Reuters' request for comments.
Wirato said that the Merakes issue has not impacted overall operations in the Bontang Liquefied Natural Gas where the project is located, but production may be slightly affected.
"Maybe it will drop a little, or we'll look for backup from other producers who can supply more," Wirato said.
Read the article online at: https://www.oilfieldtechnology.com/offshore-and-subsea/28102021/production-disrupted-at-merakes-gas-field/
You might also like
Africa needs US$375 billion to develop natural gas sector, says Society of Petroleum Engineers (SPE)
With 17 high impact wells completed in 2025, Africa will need significant investment to support natural gas demand in the near-medium term.