Audit of Lundin Norway AS – Edvard Grieg
Published by Joseph Green,
Editor
Oilfield Technology,
The Edvard Grieg field is being developed using a manned fixed facility comprising a processing facility, living quarters and drilling by means of an external jack-up drilling rig. The field is situated approximately 180 km west of Stavanger.
The objective of the audit was to assess how Lundin is ensuring compliance with regulatory requirements for barrier management in the Edvard Grieg development project.
Result
Non-conformities were identified in connection with:
- The emergency shutdown system
- Evacuation routes
An improvement point was identified in connection with deluge system automation.
Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.
Improvement point:
Entails that we have identified a deficiency, without there being sufficient grounds for determining a breach of regulatory requirements.
Adapted from press release by Joe Green
Read the article online at: https://www.oilfieldtechnology.com/exploration/06022015/audit-lundin-norway-edvard-grieg-373/
You might also like
Global gas demand 2025
If current trends persist, future energy demand will outpace demand expectations in many scenarios, positioning natural gas as the most scalable and responsive solution to meet growing power needs and stabilise grids.