Nord Stream carries out load testing
As part of the ongoing ramp-up phase and as preparation for the operation of Nord Stream as a twin-pipeline gas transportation system, Nord Stream AG is conducting load tests for Line 1. Over the past three days Line 1 has been operating at full capacity of app. 75 million m3/d which corresponds to approximately 27.5 billion m3/yr. The tests will continue for another three weeks.
During the tests, the gas transportation parameters will fluctuate in different modes. The industry standard load tests serve to confirm the safety and reliability of the pipeline. The first of Nord Stream’s twin pipelines continues to transport to its downstream European partners all the gas nominated and supplied by Gazprom Export.
Adapted from press release by Peter Farrell.
Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/24052012/nord-stream-carries-out-load-testing/
You might also like
Smart infrared: digitalising industry
Francisco Cortés, CEO, SENSIA Solutions, explains how smart infrared is changing the game for emissions monitoring, preventive maintenance, and safety in upstream oil and gas operations.