Skip to main content

Mustang will review readiness of Woodside Energy’s North Rankin B platform

Oilfield Technology,


North West Shelf Venture’s Australian operator, Woodside Energy Ltd, has selected Wood Group’s Mustang to provide the independent assessment and verification of readiness for one of the world’s heaviest open water floatover installations, the North Rankin B (NRB) platform topsides, to be located on the North West Shelf of Australia.

Breaking world records
The NRB topsides installation is significant and will break world records including the heaviest topsides (23 600 t) to be floatover installed on a steel jacket and, at a depth of 126 m (413 ft), the deepest open water floatover steel jacket.

Floatover method
The NRB topsides is an integrated floatover deck, which will be installed on the platform’s steel jacket substructure. The NRB topsides will be transported to its final location on a 20 m high deck support frame such that the topsides is floatover installed on the top of the NRB jacket at an elevation of 28 m. The floatover method eliminates the use of lifting operations and uses the transport barge itself as an installation barge. This eliminates the need for a crane vessel, which results in cost, scheduling and risk benefits.

NR2 central processing complex
The NRB platform will be similar in size to the existing North Rankin A (NRA) facility. Once installed, the NRB platform bridge linked to the existing NRA platform will form the NR2 central processing complex. The work commenced in January.

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/23032010/mustang_will_review_readiness_of_woodside_energy%E2%80%99s_north_rankin_b_platform/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Oil & gas news