GE to power Sabine Pass liquefaction project
GE Oil & Gas will supply gas compression trains for Cheniere Energy’s Sabine Pass liquefaction project.
Cheniere Energy is planning to add liquefaction capabilities to the Sabine Pass LNG terminal making it the first LNG terminal capable of importing and exporting LNG in the U.S.
GE will supply 12 PGT25+G4 aeroderivative gas turbines to drive the first two liquefaction trains of the Sabine Pass Liquefaction Project currently under construction. Each train will have the capacity to produce approximately 4.5 million tpy of LNG.
Cheniere has received regulatory approvals from the Federal Energy Regulatory Commission to construct up to four liquefaction trains at Sabine Pass. Cheniere is expected to reach a final investment decision on its third and fourth liquefaction trains in the first quarter of 2013, with construction of those trains expected to commence shortly thereafter.
Adapted from press release by Peter Farrell.
Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/09102012/ge-win-contract-for-sabine-pass-lng-compression-trains/
You might also like
3t achieves TGA accreditation for maritime training in Saudi Arabia, strengthening regional workforce development
3t, a global leading provider of safety critical training and blended learning solutions for high-hazard industries, has achieved official accreditation by the Transport General Authority (TGA) for its maritime training programmes to be delivered at its Dammam training centre.