Petrobras starts-up third well at Sapinhoá field

Oilfield Technology,


Petrobras has announced the start-up of well 7-SPH-04-SPS, at a water depth of 2120 m, in Sapinhoá field, in the Santos Basin pre-salt region. This well has an estimated production potential of 26,000 bpd of oil  and is interconnected to FPSO Cidade de São Paulo through buoyancy supported risers (BSRs).

This is the third production well of the Sapinhoá Pilot Project and the second to go in operation through the BSR gathering system, following the start-up of well SPS-77A, which has been producing approximately 36,000 bpd of oil since the 18th of February 2014.

FPSO Cidade de São Paulo has the capacity to process up to 120,000 bpd and has been in operation since January 2013, when it was directly interconnected to well SPS-55. The fourth production well of the project will be interconnected early in the second half of the year. With the start-up of this well, the platform will reach its full output capacity.

Next buoy will operate in Lula Nordeste Project

Besides the first buoy already installed in Sapinhoá field, three other similar systems have been commissioned for installation in Santos Basin pre-salt fields. Of these three, one more will be destined for Sapinhoá field (Sapinhoá Pilot Project – FPSO Cidade de São Paulo) and the other two for Lula field (Lula Nordeste Pilot Project – FPSO Cidade de Paraty).

FPSO Cidade de Paraty, with the capacity to process up to 120,000 bpd, went into operation on the 6th of June 2013 when it was directly interconnected to the output of well LL-11.

Installation of the second buoy, destined for Lula field, was completed in February in less than a third of the time it took to install the first one, thanks to improvements made to installation processes. Then, on the 9th of March, deployment of the rigid steel pipelines to gather the output from two NE Lula wells, through the buoy, was completed.

At this time, installation is underway of the flexible pipelines of well 7-LL-22D-RJS, the first production well to be connected to the Lula NE buoy. This well will go in operation this quarter. Then, two other wells will be interconnected and FPSO Cidade de Paraty will reach its full output capacity in the third quarter of this year.

Two other buoys will be installed in the first half of the year

Operations to interconnect the third buoy in Sapinhoá field are ahead of schedule. The buoy is already submerged and attached to its foundations. Installation work will be completed this quarter.

The fourth and last buoy, designed for the Lula field, is already onsite and is currently in the initial installation phase, according to schedule. Installation is also expected to be completed this quarter.

Sapinhoá field is operated by Petrobras (45%), in partnership with BG E&P Brasil Ltda (30%) and Repsol Sinopec Brasil S.A. (25%).

Lula field is operated by Petrobras (65%), in partnership with BG E&P Brasil Ltda (25%) and Petrogal Brasil S.A. (10%).

New monthly production record in the pre-salt

Petrobras has also announced that its pre-salt oil production (including Petrobras' share and that of its partners) averaged 387,000 bpd of oil in March, a new monthly output record. With this volume, Petrobras has surpassed the previous record of 385,000 bpd set in February.

Adapted from press release by Cecilia Rehn

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/07042014/petrobras_starts_up_third_well_at_sapinho%C3%A1_field_in_brazil/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Oil & gas news