McDermott completes drilling platform in Bay of Campeche
McDermott International has announced the successful completion of the Ayatsil-B drilling platform for PEMEX in the Bay of Campeche Ayatsil field.
McDermott was awarded the contract in 2012 and provided engineering, procurement, fabrication, pre-commissioning, load-out and sea fastening of the Ayatsil-B eight-leg jacket and deck, weighing approximately 11,535 tonnes in water 115 meters deep.
David Dickson, President and CEO, commented: “McDermott is proud to successfully deliver this jacket and deck to PEMEX. During the project, more than 540 personnel at our Altamira yard worked safely to complete the structure for the growing Mexican offshore market.”
McDermott completed the engineering from its network of specialist in-house engineers in Houston and Mexico City, with fabrication from its yard in Altamira, Mexico.
McDermott is contracted to provide training for PEMEX personnel for operation and maintenance of the Ayatsil-B facility. The platform is one of four to be used, along with an FPSO, to develop heavy oil from the Ayatsil field in the Bay of Campeche.
Adapted from press release by Katie Woodward
Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/03072014/mcdermott_completes_drilling_platform_for_pemex_972/
You might also like
Rhino Resources and Halliburton to sign contract for integrated deep-water services offshore Namibia
Halliburton Company has announced it has been awarded a deep water integrated multi-well construction contract by Rhino Resources, a private company engaged in both onshore and offshore energy exploration in Africa.