Tap Oil completes first three development wells

 

Oilfield Technology,

Tap Oil Limited has provided an update on the Manora Oil Development in the Northern Gulf of Thailand.

Mubadala Petroleum, operator of the Manora Oil Development joint venture, has advised the first three development wells - MNA-01, MNA-02 and MNA-03 - have now been completed. It is now expected that production will commence from all three wells, resulting in a higher initial rate than forecast with two wells. Completion on MNA-05 has now commenced.

Platform commissioning at Manora is well underway, with hook up and commissioning nearing completion. Mubadala Petroleum has advised production is now expected to commence by mid-November.

Comments

TAP Managing Director and CEO, Troy Hayden, commented: “We are pleased with the operator’s progress on the drilling. The last of the critical systems should be handed over to operations by the end of the week, with production now scheduled to commence by mid-November.

“Despite this, the operator has advised peak production remains on track to be achieved in the first quarter of 2015 due to the progress of the development drilling.”


Adapted from press release by Katie Woodward

 

Manora oil development update

Tap Oil Limited provides an update on the Manora oil development project in the Northern Gulf of Thailand.

Thailand drilling update from Carnarvon

Carnarvon Petroleum Limited has announced the following update in relation to the L44/43 and L33/43 oil and gas concessions in Thailand.


 

This article has been tagged under the following:

Oil & gas news